Project Schedule

PD&E Study Schedule
Begin PD&E Study March 15, 2024
Public Meeting July 30, 2024
Complete PD&E Study Fall 2024
Complete Design Phase Summer 2026

FDOT Adopted Five Year Work Program Fiscal Years 2024/25 to 2028/29

The Design, Right of Way and Construction phases are currently funded in FDOT’s Five-Year Work Program (Fiscal Years 2024/2025-2028/2029).

This project is included in the Pasco County MPO’s 2024 List of Priority Projects.

Phase Fiscal Year(s)
PD&E Complete
Design 2023/2024, 2024/2025
Right of Way 2024/2025
Construction* 2024/2025

*Expected Construction letting in Fiscal Year 2026/2027
 

Contact Information

For more information or to comment, please contact:

 

Charlie Xie, P.E., Project Manager
Florida Department of Transportation, District Seven
11201 N. McKinley Drive
MS 7-500
Tampa, FL 33612-6456
(813) 975-6287
(800) 226-7220
charlie.xie@dot.state.fl.us


Comuniquese Con Nosotros
Si usted tiene preguntas o comentarios o si simplemente desea mas informacion sobre este proyecto, favor de ponerse en contacto con nuestro representante, el señor Manuel Flores, al teléfono (813) 975-6279 o correo electrónico manuel.flores@dot.state.fl.us.