{"id":91,"date":"2012-10-10T14:54:43","date_gmt":"2012-10-10T14:54:43","guid":{"rendered":"http:\/\/www.qcmywebsite.com\/fluid\/?page_id=91"},"modified":"2026-09-23T11:42:38","modified_gmt":"2026-09-23T16:42:38","slug":"project-schedule","status":"publish","type":"page","link":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/project-schedule\/","title":{"rendered":"Project Schedule"},"content":{"rendered":"<p>The I-175 Action Plan began in January 2025, and is planned to be completed by the end of 2026. The project activities include collecting information, defining a vision for the corridor, and developing corridor alternatives. Please see the project schedule below.<\/p>\n<p><a href=\"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04.jpg\"><img loading=\"lazy\" decoding=\"async\" src=\"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04.jpg\" alt=\"\" width=\"2125\" height=\"445\" class=\"alignright size-full wp-image-1293\" srcset=\"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04.jpg 2125w, https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04-300x63.jpg 300w, https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04-1024x214.jpg 1024w, https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04-768x161.jpg 768w, https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04-1536x322.jpg 1536w, https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-content\/uploads\/sites\/132\/Schedule_Website_04-2048x429.jpg 2048w\" sizes=\"(max-width: 2125px) 100vw, 2125px\" \/><\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>The I-175 Action Plan began in January 2025, and is planned to be completed by the end of 2026. The project activities include collecting information, defining a vision for the corridor, and developing corridor alternatives. Please see the project schedule<span class=\"ellipsis\">&hellip;<\/span><\/p>\n<div class=\"read-more\"><a href=\"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/project-schedule\/\">Read more &#8250;<\/a><\/div>\n<p><!-- end of .read-more --><\/p>\n","protected":false},"author":1,"featured_media":0,"parent":0,"menu_order":0,"comment_status":"closed","ping_status":"closed","template":"","meta":{"_acf_changed":false,"footnotes":""},"acf":[],"_links":{"self":[{"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/pages\/91"}],"collection":[{"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/pages"}],"about":[{"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/types\/page"}],"author":[{"embeddable":true,"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/users\/1"}],"replies":[{"embeddable":true,"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/comments?post=91"}],"version-history":[{"count":14,"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/pages\/91\/revisions"}],"predecessor-version":[{"id":1294,"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/pages\/91\/revisions\/1294"}],"wp:attachment":[{"href":"https:\/\/www.fdotd7studies.com\/projects\/i-175-action-plan-study\/wp-json\/wp\/v2\/media?parent=91"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}