The McIntosh Road PD&E study began in late 2021. The project activities include collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build” alternatives. A public hearing is scheduled for November 14th, 2024, and the study is expected to be completed in the Fall of 2024.
| PD&E Study Schedule | |
| Study Began | Late 2021 |
| Data Collection | Completed Spring 2023 |
| Preparation of Documents | Ongoing |
| Public Hearing | November 14th, 2024 |
| PD&E Study Approval | Winter 2025 |