Project Schedule

The SR 56 PD&E study began in the Summer of 2019. The project activities include collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build alternatives.” An opportunity to request a public hearing was advertised in September 2021. The study is expected to be completed in late 2022 following approval of an Interchange Access Request.

PD&E Study Schedule
Begin PD&E Study Summer 2019
Data Collection Fall/Winter 2020
Engineering & Environmental Analysis Spring/Summer 2021
Opportunity to Request a Public Hearing September 2021
Interchange Access Request End 2021-Mid 2022
Study Complete End 2022

 

Contact Information
For more information about this project, please contact:

Environmental Management Office
Florida Department of Transportation, District Seven
11201 N. McKinley Drive
M.S. 7-500
Tampa, FL 33612-6456

Phone: (813) 975-6000
Toll Free: (800) 226-7220

Comuniquese Con Nosotros

Nos importa mucho la opinión del público sobre el proyecto. Si usted tiene preguntas o comentarios, o si simplemente desea más información, por favor comuníquese con nosotros. Nuestro representante en español es: Maidolys Aguado, 813-975-6766, Departamento de Transporte de la Florida, 11201 N. McKinley Dr., MS-7-350, Tampa, FL 33612. maidolys.aguado@dot.state.fl.us