The SR 50 PD&E study began in late 2014. The project activities included collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build” alternatives. A public hearing was held on Tuesday, December 10, 2019 and the study is expected to be completed in the second quarter of 2020.
PD&E Study Schedule | |
PD&E Study Begins | Q2 2014 |
Data Collection & Traffic Analysis | Q1 2018 |
Develop & Evaluate Alternatives | Q1 2018 – Q2 2019 |
Prepare Draft Reports | Q1 2018 – Q4 2019 |
Held Public Hearing | Q4 2019 |
Prepare Final Reports | Q1 2020 – Q2 2020 |
Final FHWA Approval | Q2 2020 |