The SR 60/Courtney Campbell Causeway PD&E study began in June 2025. The project activities include collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build” alternatives. A public kickoff meeting is scheduled for the September 4, 2025. The study is expected to be completed in the third quarter of 2027.
PD&E Study Schedule | |
Study Began | June 2025 |
Kickoff Meeting | September 4, 2025 |
Public Involvement / Newsletters (2) | Fall 2025 / Summer 2026 |
Data Collection | Fall 2025 |
Engineering & Environmental Analysis | Summer 2026 |
Draft and Final Study Documents | Spring 2027 |
Public Hearing | Fall 2026 |
Final PD&E Approval | Spring 2027 |