The SR 60/Courtney Campbell Causeway PD&E study began in June 2025. The project activities include collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build” alternatives. A public kickoff meeting is scheduled for the September 4, 2025. The study is expected to be completed in the third quarter of 2027.
| PD&E Study Schedule | |
| Study Began | June 2025 | 
| Kickoff Meeting | September 4, 2025 | 
| Public Involvement / Newsletters (2) | Fall 2025 / Summer 2026 | 
| Data Collection | Fall 2025 | 
| Engineering & Environmental Analysis | Summer 2026 | 
| Draft and Final Study Documents | Spring 2027 | 
| Public Hearing | Fall 2026 | 
| Final PD&E Approval | Spring 2027 | 