The SR 60/Courtney Campbell Causeway PD&E study began in June 2025. The project activities include collecting information, developing roadway improvement alternatives and evaluating the potential environmental and social effects of the “no-build” and “build” alternatives. A public kickoff meeting was held on September 4, 2025. The study is expected to be completed in the first quarter of 2027.
| PD&E Study Schedule | |
|---|---|
| Study Began | June 2025 |
| Kickoff Meeting | September 4, 2025 |
| Public Involvement / Newsletters (2) | Fall 2025 / Summer 2026 |
| Data Collection | Fall 2025 |
| Engineering & Environmental Analysis | Summer/Fall 2026 |
| Draft and Final Study Documents | Fall 2027 |
| Public Hearing | Fall 2027 |
| Final PD&E Approval | Winter 2028 |