The US 92 (SR 600) PD&E Study Reevaluation began in January 2015. The project activities included collecting information and reevaluating roadway improvements and the associated environmental and social effects. A public hearing was held in the Fall of 2016.
- PD&E Reevaluation Initiated | January 2015
- Project Kickoff | Spring/Summer 2015
- Public Hearing | Fall 2016
- Complete PD&E Study | Spring 2018